The ground floor scaffolding on 96 De Beauvoir Road is now complete, with the next stage due to be assembled over the coming weeks.
The temporary roof cover is currently being erected over 96 De Beauvoir Road, in preparation for the removal of the windows, doors, and rooflights and the examination of the roof Pods.
Scaffolding will begin at the 3rd floor level on 94 De Beauvoir Road W/C 5th August 2024, and is due to be assembled in the autumn.
For reference, 94 is the building front and rear where the café and reception are located, and 96 is the building with the vehicle gate.
Understandably, we are anticipating noise disturbance during this period, initially with the erection of scaffolding. However, we will be working closely with the contractors to ensure disruption is kept to a minimum.
Please note, access into the Block is unaffected and you can still use the onsite café, meeting room, co-working space, delivery lock-ups and reception as usual.
Our next update will be at the end of August.